05/31/2024 - 16:30
Update 01: The first truck is bringing 6,000 gallons has just arrived onsite and is beginning to set up the temporary water feeds, our second supply truck is expected onsite in 45 minutes and will be bringing an additional 2,000 gallons. Our third truck is expected onsite in less than 10 hours. Temperatures in the second and eighth floor spaces remain in normal ranges. The city has not provided an expected permeant restoration time of city water as such.
-------------------------------------------------------------------------
05/31/2024 - 15:30
Downtown Atlanta is experiencing a major water main break. Our Atlanta datacenter is currently without water which affects the ability to operate air conditioning. We are monitoring the situation and will let you know if we see any potential outages.
Here is the update provided by the building owners.
Building engineers and Metro Fiber Systems continue to work through planned emergency water mobilization procedures. We have been provided an update from the building engineers that their water truck arrival time is estimated at 2 hours, our water mobilization truck is estimated at 12 hours. Temperatures remain within normal temperature levels.
https://www.atlantanewsfirst.com/2024/05/31/large-water-main-break-causing-issues-across-downtown-atlanta/
fredag, Maj 31, 2024